Building a Resilient Foundation for a Digital-First Guest Experience
During this reporting period, the IT & Digital Transformation team executed a dual-track strategy: stabilizing and securing core operational IT while laying the strategic groundwork for a unified digital ecosystem. Our focus has been on moving from reactive support to proactive, data-driven management and planning transformative guest experiences.
Transitioned from ad-hoc tracking to a systematic, centralized IT Asset Management System.
| Category | Status Tracking | Key Action | Impact Metric |
|---|---|---|---|
| Hardware (PCs, Printers) |
In Use / Spare / Scrap | Tagged, assigned to user/department, disposal process defined | Goal: Reduce loss by 30% in Q1 |
| Network Equipment | In Use / Under Repair | Mapped to network diagrams for fault isolation | Improved Mean Time to Repair (MTTR) |
| Software Licenses | In Stock / In Use | Centralized repository with renewal dates | Eliminate compliance risk; optimize spend |
| Critical Spares | Spare Parts | Dedicated, logged inventory for switches, APs, etc. | Reduced downtime for critical failures |
Professionalizing IT support with measurable SLAs and proper issue tracking.
4 sessions conducted for 12 key staff
Initial feedback indicates significant reduction in informal requests
Digital Exit Portal in development to automate clearance workflows
Partnering with HR Manager Mohamed Kassam on technical recruitment
Formalizing IT asset lifecycle management
Azure Migration planning for website and CMS
Implementing Google Tag Manager for data-driven marketing
Collaboration with Melvin Velásquez & Ravand
School Portal business analysis complete
Will allow schools to self-serve with automatic package logic
Integration with Galaxy POS for booking creation
We have initiated collaboration with Dr. Ahmed to optimize the EasyVet system, focusing on:
Next Steps: Requirements gathering session scheduled for first week of February 2026.
| Project | Status | Progress | Key Milestone | Department |
|---|---|---|---|---|
| Digital Screen Ecosystem | Awaiting Budget | 30% | CMS Design Complete | Marketing |
| VIP Experience Enhancement | Blueprint Phase | 40% | Requirements Gathering | Guest Services |
| Visitor Gate Automation | Integration Phase | 70% | Galaxy POS Integration | Operations |
| School Portal Development | Planning | 25% | BA Complete | Sales |
| Unified System (Unifin) | BRD Development | 50% | Stakeholder Interviews | All Departments |
Digital screen locations, network infrastructure points, and proposed unified system integration hubs
"Label First" Initiative: All core network switches being labeled
Cabling & Fiber Audit: 40% complete
Hotel Network: Revamp plan scheduled for next month
Current server room lacks proper cooling and access control
Plan: Relocate to new climate-controlled room
DR Site: Existing room to become live DR site
Strategic Imperative: The following decisions are required to maintain project momentum and achieve 2026 digital transformation goals.
| Priority | Item | Description | Decision Required By | Impact |
|---|---|---|---|---|
| P1 | Unified System (Unifin) BRD | Approve budget and form dedicated project team | Group CEO / CFO | Transformational |
| P1 | Network & Server Revamp | Approve CapEx for cabling, new server room build, and DR hardware | CFO / Operations Director | Foundation |
| P2 | Digital Screen Ecosystem | Release first-phase budget for CMS and 10 pilot screens | Marketing / Operations Director | Guest Experience |
| P2 | School Portal Development | Approve development quote and 3-month timeline | Head of Sales / CFO | Revenue & Efficiency |
Dr. Ahmed (EasyVet): Requirements gathering session for system optimization
Operations Team: Deep dive on gate automation analytics
Marketing: Finalize digital screen content strategy